Kaifeng magnetic flowmeter

2019-12-22 20:09:57

Kaifeng magnetic flowmeter

In order to make the electromagnetic flowmeter work stably and reliably, the following aspects should be noted when selecting the installation location:
1. Try to avoid ferromagnetic objects and equipment with strong electromagnetic fields (large motors, large transformers, etc.) to prevent the magnetic field from affecting the working magnetic field and flow signal of the sensor.
2. It should be installed in a dry and ventilated place to avoid sun and rain. The ambient temperature should be -20~+60°C, and the relative humidity is less than 85%.
3. There should be plenty of space around the flowmeter for easy installation and maintenance.
Installation suggestions:
The measurement principle of the electromagnetic flowmeter does not depend on the characteristics of the flow. If there is a certain turbulence and vortex in the pipeline, it will be generated in the non-measurement zone (such as elbow, tangential current limit or half-opening shut-off valve upstream). Nothing.
If steady-state eddy currents in the measurement zone affect the stability of the measurement and the accuracy of the measurement, then some measures should be taken to stabilize the flow rate distribution:
a.increase the length of the straight pipe before and after; b. use a flow stabilizer; c. reduce the cross section of the measuring point.

Kaifeng magnetic flowmeter

Working principle and sensor parameters of ultrasonic external clamp flow meter
External clip type ultrasonic flow meter external clip type ultrasonic flow meter series measuring full flow of liquid flow meter, optional explosion-proof and intrinsically safe type, explosion-proof grade Exd[ib]IIBT6, and optional intrinsically safe remote control, explosion-proof grade ExibIIBT6, measurable medium: drinking water, river water, sea water, ground water cooling water, high temperature water, sewage, lubricating oil, diesel, fuel chemical liquid, other homogeneous fluid.
External clip sensor parameters:
The external clip type sensor is an installation method in which the sensor is directly bundled on the outer surface of the pipe to be measured to realize flow measurement, and has a diameter independent of the pipe diameter.
Simple installation, no need to stop production, no pressure loss and so on.

Kaifeng magnetic flowmeter

First, the gas turbine flowmeter installation requirements
1. When the gas flowmeter is installed, it is strictly forbidden to directly conduct electric welding at the inlet and outlet flanges to avoid burning the internal parts of the flowmeter;
2. For the newly installed or overhauled pipeline, it must be purged to remove the debris in the pipeline before installing the flowmeter;
3. The gas turbine flowmeter should be installed in a place that is easy to maintain, has no strong electromagnetic field interference, no mechanical vibration and thermal radiation;
4. Gas turbine flowmeters should not be used in places where flow is frequently interrupted and there is strong pulsating flow or pressure pulsation;
5, the gas turbine flowmeter should ensure that the pipeline is coaxial, and prevent the gasket from protruding into the pipeline, otherwise it will disturb the flow profile;
6. The flow direction of the gas turbine flowmeter should be consistent with the direction marked on the casing. The upper and lower pipelines of the flowmeter should be guaranteed with 2DN and 1DN straight pipe sections;
7. When using external power supply, the flowmeter must have reliable grounding, but it should not share the grounding wire with the high-power system; when the pipeline is installed or repaired, the grounding wire of the welding system should not be overlapped with the flowmeter.
8. Since the flowmeter needs to be repaired and calibrated, in order to ensure normal gas supply, bypass piping should be set. The bypass pipe valve must be closed during normal use;
9. When constructing pipelines, it is advisable to install telescopic tubes or bellows to avoid serious stretching and causing breakage of the flowmeter;
10. When the gas turbine flowmeter is installed outdoors, the upper part should be covered to prevent the rainwater from immersing and the sun exposure affecting the service life of the flowmeter;
11. When installing the gas turbine flowmeter, it is advisable to add a filter to the flowmeter (filtering accuracy is recommended ≤20μm).
Second, gas turbine flowmeter requirements
1. When the gas turbine flowmeter is put into operation, the upstream valve of the flowmeter should be slowly opened (not less than 15 seconds), and then the downstream valve of the flowmeter should be slowly opened to prevent the instantaneous airflow from rushing to the turbine;
2. When the flowmeter needs to have a long-distance signal, it should be connected to the external power supply (+12~+24VDC) strictly according to the electrical performance index of the gas turbine flowmeter. It is strictly forbidden to directly connect 220VAC (or 380VAC) power supply at the signal output.