Abb Flow Meter

2020-05-17 06:38:12

Abb Flow Meter

To ensure the measurement accuracy of the electromagnetic flowmeter, proper installation is very important.
The transmitter should be installed in a dry and ventilated place indoors. Avoid installation in places where the ambient temperature is too high, should not be subject to strong vibration, try to avoid equipment with strong magnetic fields, such as large motors, transformers, etc. Avoid installation in corrosive gases. The installation location is easy to overhaul. This is the environmental condition to ensure the normal operation of the transmitter.
In order to ensure that the measuring tube of the transmitter is filled with the measured medium, the stacker is preferably installed vertically, and the flow direction is from bottom to top. Especially for liquid-solid two-phase flow, it must be installed vertically. If the site is only allowed to be installed horizontally, it must be ensured that the two electrodes are at the same level.
The transmitter should be equipped with valves and bypass at both ends.
The millivolt AC potential measured by the electrode of the electromagnetic flow transmitter is based on the liquid potential in the transmitter. In order to stabilize the liquid potential and maintain the potential of the transmitter and fluid to ensure stable measurement, the transmitter shell and the metal tube should have good grounding at both ends, and the converter housing should also be grounded. The grounding resistance should not be greater than 10 and cannot be shared with the grounding wire of other electrical equipment. If the transmitter housing is not guaranteed to be in good contact with the metal pipe, connect them with metal wires. Re-reliable grounding.
In order to avoid interference signals, the signal between the transmitter and the converter must be transmitted with shielded wires. It is not allowed to place the signal cable and power cable in parallel in the same cable. The length of the signal cable should generally not exceed 30 m.
Converter installation site should avoid AC and DC strong magnetic field and vibration, ambient temperature is -20 to 50 ° C, does not contain corrosive gases, relative humidity is not more than 80%.
In order to avoid the influence of the flow rate on the relative measurement, the flow regulating valve should be placed downstream of the transmitter. For small-caliber transmitters, since the distance from the center of the electrode to the inlet end of the flowmeter is equivalent to several times the length of the diameter D, the upstream straight pipe may not be specified. However, for a flowmeter with a large diameter, generally there should be a straight pipe section of 5D or more in the upstream, and the downstream pipe section is generally not required.

Abb Flow Meter

Second, the compressed air vortex flowmeter installation steps
1. The special flanges to be equipped are welded to the upstream and downstream straight pipe sections respectively, so that the inner diameters of the special flange and the straight pipe section are strictly vertical and concentric.
2. Install the sensor clip on the upper and lower straight pipe sections welded with special flanges and fasten them with bolts. The upstream and downstream straight sections should be kept concentric with the sensor.
3. It should be noted that the flow direction of the sensor should be consistent with the flow direction of the fluid in the pipeline.
Third, special attention should be paid when installing compressed air vortex flowmeter
1. When welding special flanges and straight pipe sections, the sensor should be removed and the sensor welding flange must not be carried.
2. Before the sensor is installed, the sealing ring must be placed in the groove of the flange.
3. The pressure point and temperature measurement point should be at the 3DN~5DN and 6N~8DN downstream of the sensor.
4. When the high temperature pipeline is insulated, do not wrap the sensor to avoid damage.
5. The cable connecting the vortex flowmeter should be as far away as possible from the interference of strong electromagnetic fields. It is absolutely not allowed to lay with high voltage cables. The shielded cable should be as short as possible, the maximum length should not exceed 500 meters, and should not be coiled to reduce the distributed inductance.

Abb Flow Meter

Selection of measurement types for special industrial and commercial users
    2. Case 2: A heavy machine tool factory
    The main gas plant of the heavy-duty machine tool factory is 13 production kiln, and there is also a machine repair workshop and 63 mobile burners. The total gas load of all gas facilities is 1837m3/h. See Table 1 for details. The customer promised that all gas facilities could not be fully activated at the same time, the maximum gas consumption required was 1200m3/h, and the minimum pressure required before the furnace was 0.055MPa. The pressure regulator used in the on-site pressure regulating metering box is opened and ready, and the flow meter is in the form of a G1600 turbine table plus bypass.
    When debugging the kiln, it was found that the flowmeter in the pressure regulating metering box had a stop-and-go phenomenon. If only some of the kiln was opened or only some of the kiln was used, there would be a phenomenon that the flowmeter did not measure or the measurement error was large.